Client:

Walls Construction

Scope:

Design, Supply & Installation of Post-Tensioning

Completion:

2019

 

The Office Development at Arkle Road, Sandyford, consists of a 6 storey building covering an area of 19,600m2. Termini is located in Sandyford, Dublin.  It boasts large floor plates of up to 19,000sqm and floor to ceiling heights of 3m.

www.Termini.ie  

ClearTech’s scope covered the design, supply and installation of post tensioning.   Working on 3 pours per floor and bringing back the delayed programme, helping the Contractor to reach his target dates.  Project completed on time and within budget.